For the latest information on the construction at Franklin, please click on the link: Construction Updates For the Week of November 17-21, the following was completed: *Completed subgrade preparation for slab. *Completed conduit and wiring for relocation of VFD’s and EF controls in boiler room. *Continued submittal process. For the Week of November 24-28, the following was to be completed: *Concrete pour for slab on grade is scheduled for Wednesday, November 26th. *Pre-erection meeting scheduled for Wednesday, November 26th. *Pour concrete footings for elevator pit. *Continue submittal process.