Franklin Construction Updates, December 1-12

Activities during the week of December 1-5:

*Commenced installation of structural steel and metal decking.

*Commenced underpinning at elevator addition.

*Completed concrete pour at areaways on North and South sides of addition.

*Continued submittal process.

 

Anticipated activities during the Week of December 8-12:

*Continued steel erection.

*Continued underpinning at elevator addition.

*Continued submittal process.