Activities during the week of December 1-5:
*Commenced installation of structural steel and metal decking.
*Commenced underpinning at elevator addition.
*Completed concrete pour at areaways on North and South sides of addition.
*Continued submittal process.
Anticipated activities during the Week of December 8-12:
*Continued steel erection.
*Continued underpinning at elevator addition.
*Continued submittal process.