Daily Archives: December 14, 2014

Activities during the week of December 1-5: *Commenced installation of structural steel and metal decking. *Commenced underpinning at elevator addition. *Completed concrete pour at areaways on North and South sides of addition. *Continued submittal process.   Anticipated activities during the Week of December 8-12: *Continued steel erection. *Continued underpinning at elevator addition. *Continued submittal process.              