Week of August 18th:
*Completed construction of new partition for temporary egress and fire rated ceiling.
*Completed electrical work for temporary egress.
*Completed installation of exterior temporary egress door.
*Commenced sheetrock ceiling in temporary egress corridor.
*Commenced installation of lighting in temporary corridor.
*Commenced installation of temporary egress steps on South side of building.
*Commenced excavation of building addition footprint.
*Continued submittal process.
Anticipated for Week of August 25th:
*Complete sheet rocking of ceilings at temporary egress corridor.
*Complete installation of light fixtures and exit signs at temporary egress corridor.
*Continue excavation of building addition footprint.
*Commence excavation of elevator footprint.
*Continue submittal process.