Week of August 18th: *Completed construction of new partition for temporary egress and fire rated ceiling. *Completed electrical work for temporary egress. *Completed installation of exterior temporary egress door. *Commenced sheetrock ceiling in temporary egress corridor. *Commenced installation of lighting in temporary corridor. *Commenced installation of temporary egress steps on South side of building. *Commenced excavation of building addition footprint. *Continued submittal process. Anticipated for Week of August 25th: *Complete sheet rocking of ceilings at temporary egress corridor. *Complete installation of light fixtures and exit signs at temporary egress corridor. *Continue excavation of building addition footprint. *Commence excavation of elevator footprint. *Continue submittal process.