Franklin School – General Construction Meeting FLIC June 23, 2014 Construction Timeline: – Project Duration approximately 16 months (June 2014-Sept 2015). – Work will begin Thursday, June 26th. – A six ft. high chain link security fence will be erected on 6/26 to contain the construction site. – They will build the addition first to open up new space. Followed by the interior renovation of the main office in the summer of 2015. – The construction trailers that are currently in place will remain there until the end of the project. The anticipated removal date is Sept 2015. The modular classrooms will also be removed at that time. For updates regarding Construction: http://www.summit.k12.nj.us/Board_of_Education/0137B153-000F8CAF?plugin=RWD&Templates=RWD&object=BOE_News/Construction%20Updates%20&infobar=no&ConfPosition=2 Safety Notes: -The contractor has completed background checks on all employees. All contraction workers must wear a yellow ID badge while on site. If you see anyone suspicious without a badge call the police. Other information: -Construction workday is from 7am to 3:30pm. To comply with the town noise ordinance no noise before 8am. -Occasional weekend work may occur. -Construction workers will park in the school parking lot during the summer months. Once school begins they will park on the street. There will be approximately 25 workers
[…]