Activities during the week of January 12, 2015 – January 16, 2015
Franklin Elementary School Construction Update
- ·Continued installation of structural steel and metal decking.
- ·Completed subgrade prep at new entrance near elevator addition.
- ·Completed concrete pour of footings at new entrance near elevator addition.
- ·Continued construction of mock up panel for masonry.
- ·Continued submittal process.