For the latest information on the construction at Franklin, please click on the link: Construction Updates
For the Week of November 17-21, the following was completed:
*Completed subgrade preparation for slab.
*Completed conduit and wiring for relocation of VFD’s and EF controls in boiler room.
For the Week of November 24-28, the following was to be completed:
*Concrete pour for slab on grade is scheduled for Wednesday, November 26th.
*Pre-erection meeting scheduled for Wednesday, November 26th.
*Continue submittal process.