136 Blackburn Road, Summit, NJ

Franklin Elementary PTO

logo

Franklin Construction Updates, Nov. 17-28

For the latest information on the construction at Franklin, please click on the link: Construction Updates

 

For the Week of November 17-21, the following was completed:

*Completed subgrade preparation for slab.

*Completed conduit and wiring for relocation of VFD’s and EF controls in boiler room.

*Continued submittal process.

For the Week of November 24-28, the following was to be completed:

*Concrete pour for slab on grade is scheduled for Wednesday, November 26th.

*Pre-erection meeting scheduled for Wednesday, November 26th.

*Pour concrete footings for elevator pit.

*Continue submittal process.

 

Comments are closed.

Past Posts